Scheme Details
DISTRICT
Saharanpur
AGENCY
Gayatri Projects LTD
SCHEME ID
8359154
SCHEME NAME
Sadhauli Hariya Must
ESTIMATED COST
247.98
EXPENDITURE
64.83
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
18
Procured
23
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
9913.00
Meter
Length Laid
9743.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Saharanpur | Rampur Maniharan | Sadhauli Hariya Must. | 384333 | Sadhauli Hariya Must. | 447 | 447 | 100% | Har Ghar Jal | Not Certified |
| 2 | Saharanpur | Rampur Maniharan | Sadhauli Hariya Must. | 384334 | SARGATHAL MU. | 72 | 70 | 97% | Work In Progress | Not Certified |