Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Deoria | Gayatri Projects LTD | 8359331 | Deoria Dhus G.P. water Supply Scheme | 280.07 | 151.76 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 22 | 19 | Yes | 0 | NA | No | 16806.00 | 15800.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Deoria | Pathardewa | Deoria | 459095 | Deoria | 182 | 182 | 100 | Har Gar Jal | Not Certified | 
| 2 | Deoria | Pathardewa | Deoria | 459096 | Koeri Patti | 174 | 157 | 90 | Work In Progress | Not Certified |