Scheme Details
DISTRICT
Deoria
AGENCY
Gayatri Projects LTD
SCHEME ID
8359408
SCHEME NAME
Chirawn Buzurg G.P. water Supply Scheme
ESTIMATED COST
329.65
EXPENDITURE
185.45
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
1
Solar Plant
Required
33
Procured
33
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
13253.00
Meter
Length Laid
12960.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Deoria | Gauri Bazar | Chriaw Buzurg | 459323 | Chriaw Buzurg | 731 | 729 | 100% | Work In Progress | Not Certified |
| 2 | Deoria | Baitalpur | Araipar | 459346 | Araipar | 356 | 356 | 100% | Har Ghar Jal | Not Certified |