Scheme Details
DISTRICT
Deoria
AGENCY
Gayatri Projects LTD
SCHEME ID
8359924
SCHEME NAME
Chiuraha Khas G.P. water Supply Scheme
ESTIMATED COST
305.76
EXPENDITURE
172.78
AUTOMATION STATUS
Disconnected
View Live Screen
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
29
Procured
27
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
14888.00
Meter
Length Laid
14030.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Deoria | Baitalpur | Bahorpur | 459339 | Bahorpur | 226 | 226 | 100% | Har Ghar Jal | Not Certified |
| 2 | Deoria | Baitalpur | CHIURAHA KHAS | 459422 | CHIURAHA KHAS | 543 | 543 | 100% | Har Ghar Jal | Not Certified |