Scheme Details
DISTRICT
Bijnor
AGENCY
LC INFRA
SCHEME ID
8360392
SCHEME NAME
AKBARPUR MAJRA SAINDWAR VILLAGE WATER SCHEME
ESTIMATED COST
305.47
EXPENDITURE
253.15
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
5
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
18
Procured
18
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
11191.00
Meter
Length Laid
11191.00
Meter
Scheme Assigned Villages
5 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Jalilpur | Akbarpur Majra Saindwar | 387373 | Akbarpur Majra Saindwar | 184 | 184 | 100% | Har Ghar Jal | Not Certified |
| 2 | Bijnor | Jalilpur | Akbarpur Majra Saindwar | 387374 | Malakpur | 104 | 104 | 100% | Har Ghar Jal | Not Certified |
| 3 | Bijnor | Jalilpur | Akbarpur Majra Saindwar | 387375 | Fareedpur Meghoo Urf Towekpuri | 8 | 8 | 100% | Har Ghar Jal | Not Certified |
| 4 | Bijnor | Jalilpur | Akbarpur Majra Saindwar | 387376 | Afzalpur Urf Chootapur | 58 | 58 | 100% | Har Ghar Jal | Not Certified |
| 5 | Bijnor | Jalilpur | Akbarpur Majra Saindwar | 387377 | Simili | 31 | 31 | 100% | Har Ghar Jal | Not Certified |