| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Moradabad | LC INFRA | 8360512 | Sehali Mustahkam Village Water Supply Scheme | 203.48 | 114.92 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 25 | 25 | Yes | 0 | NA | No | 6281.00 | 6000.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Moradabad | Moradabad | SEHALI MUSTAHKAM | 388254 | Sehali Mustahkam | 471 | 445 | 94 | Work In Progress | Not Certified |
| 2 | Moradabad | Moradabad | SEHALI MUSTAHKAM | 681442 | Sehali Ahatmali | 4 | 1 | 25 | Work In Progress | Not Certified |