Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Varanasi | Larsen & Toubro Ltd | 8360643 | Balua | 393.08 | 259.12 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 25 | 25 | No | 0 | NA | No | 21260.00 | 21260.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Varanasi | HARAHUA | BALUA | 476046 | BALUA | 442 | 442 | 100 | Har Gar Jal | Not Certified | 
| 2 | Varanasi | HARAHUA | BALUA | 476047 | DHURIPUR | 149 | 148 | 99 | Work In Progress | Not Certified | 
| 3 | Varanasi | HARAHUA | BALUA | 476048 | BARVAPUR | 95 | 90 | 95 | Work In Progress | Not Certified | 
| 4 | Varanasi | HARAHUA | BALUA | 476049 | ITWA | 38 | 34 | 89 | Work In Progress | Not Certified | 
| 5 | Varanasi | HARAHUA | BALUA | 659829 | TEKIPUR | 102 | 101 | 99 | Work In Progress | Not Certified |