Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Varanasi | Larsen & Toubro Ltd | 8360722 | Isharwar | 288.38 | 217.51 | view more | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 18 | 18 | Yes | 0 | NA | No | 13385.00 | 13372.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Varanasi | Sewapuri | Esar War | 476145 | Esar War | 306 | 306 | 100 | Har Gar Jal | Certified | 
| 2 | Varanasi | Sewapuri | Esar War | 476146 | Machiyar | 137 | 137 | 100 | Har Gar Jal | Certified | 
| 3 | Varanasi | Sewapuri | Esar War | 476147 | Gopalpur | 27 | 27 | 100 | Har Gar Jal | Certified |