Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Deoria | LC INFRA | 8360776 | Deidihi GP water supply scheme | 284.54 | 195.25 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 24 | 24 | No | 0 | NA | No | 12014.00 | 10050.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Deoria | Barhaj | Deidihi | 460088 | Deidihi | 240 | 238 | 99 | Work In Progress | Not Certified |
| 2 | Deoria | Barhaj | Deidihi | 460089 | Bharsara | 123 | 105 | 85 | Work In Progress | Not Certified |
| 3 | Deoria | Barhaj | Deidihi | 460090 | Raipura Chacklal | 223 | 218 | 98 | Work In Progress | Not Certified |