Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Prayagraj | Larsen & Toubro Ltd | 8360804 | Akdala Gram Panchayat Multi Villages Water Suply Scheme | 361.19 | 172.80 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 28 | 28 | Yes | 0 | NA | No | 14279.00 | 14279.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Prayagraj | SAHSON | AKDALA | 432304 | AKDALA | 265 | 247 | 93 | Work In Progress | Not Certified |
| 2 | Prayagraj | SAHSON | AKDALA | 432305 | BHARAHRI | 70 | 56 | 80 | Work In Progress | Not Certified |
| 3 | Prayagraj | SAHSON | AKDALA | 432306 | FIROZPUR TA.BHARAHRI | 88 | 70 | 80 | Work In Progress | Not Certified |