Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Gonda | Larsen & Toubro Ltd | 8360877 | Hind Nagar Banki | 296.57 | 144.70 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 21 | 21 | Yes | 0 | NA | No | 14615.00 | 10568.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gonda | Rupaidih | Hind Nagar Banki | 444516 | Achal Nagar | 152 | 142 | 93 | Work In Progress | Not Certified |
| 2 | Gonda | Rupaidih | Hind Nagar Banki | 444517 | Amwakhudai Nagar | 80 | 71 | 89 | Work In Progress | Not Certified |
| 3 | Gonda | Rupaidih | Hind Nagar Banki | 444518 | Hind Nagar Banki | 198 | 198 | 100 | Har Gar Jal | Not Certified |