Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Chandauli | ION EXCHANGE | 8361050 | Shahpur GP | 391.86 | 51.49 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 2 | 2 | 2 | 2 | 1 | 0 | 0 | 11 | 11 | Yes | 0 | NA | No | 8000.00 | 8000.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Chandauli | Shahabganj | Shahpur | 475254 | Shahpur | 243 | 243 | 100 | Har Gar Jal | Not Certified |
| 2 | Chandauli | Shahabganj | Shahpur | 475255 | Usari | 104 | 104 | 100 | Har Gar Jal | Not Certified |
| 3 | Chandauli | Shahabganj | Shahpur | 475374 | Nikandopur | 22 | 22 | 100 | Har Gar Jal | Not Certified |
| 4 | Chandauli | Shahabganj | Shahpur | 657379 | Salavtpur | 10 | 10 | 100 | Har Gar Jal | Not Certified |