Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Gorakhpur | NCC Ltd. | 8361209 | Kotiya Bishuni | 252.40 | 221.15 | Verified | Verified | view more |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Gorakhpur | Belghat | KOTIYA BISHUNI | 456878 | Kotiya Bishuni | 113 | 113 | 100 | Har Gar Jal | Certified | Verified |
2 | Gorakhpur | Belghat | KOTIYA BISHUNI | 456879 | Jagakol | 57 | 57 | 100 | Har Gar Jal | Certified | Verified |
3 | Gorakhpur | Belghat | KOTIYA BISHUNI | 456880 | Bistuie | 59 | 59 | 100 | Har Gar Jal | Certified | Verified |
4 | Gorakhpur | Belghat | KOTIYA BISHUNI | 696392 | CHAKDAUD | 6 | 6 | 100 | Har Gar Jal | Certified | Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
4 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 22 | 22 | Yes | 0 | NA | No | 4382.00 | 6868.00 |