Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Bareilly | NCC Ltd. | 8361224 | PAUNAGLA | 337.24 | 177.11 | Verified | Verified | view more |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Bareilly | Bhuta | Paunagla | 404153 | Paunagla | 199 | 199 | 100 | Har Gar Jal | Certified | Verified |
2 | Bareilly | Bhuta | Paunagla | 404154 | Udharanpur Ilaka Budhauli | 143 | 143 | 100 | Har Gar Jal | Certified | Not Verified |
3 | Bareilly | Bhuta | Paunagla | 404155 | Dandia Sitabrai | 66 | 66 | 100 | Har Gar Jal | Certified | Not Verified |
4 | Bareilly | Bhuta | Jataua | 404156 | BRAHAMPUR NAWADIA | 13 | 13 | 100 | Har Gar Jal | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 22 | 22 | Yes | 0 | NA | No | 10082.00 | 10051.00 |