Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Fatehpur | Gayatri Projects LTD | 8361237 | Jagannathpur | 246.27 | 130.81 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 20 | 20 | Yes | 0 | NA | No | 9635.00 | 8954.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Fatehpur | Teliyani | Jagannathpur | 427742 | Jagannathpur | 227 | 227 | 100 | Har Gar Jal | Not Certified |
| 2 | Fatehpur | Teliyani | Jagannathpur | 427743 | Bari Govindpur | 167 | 167 | 100 | Har Gar Jal | Not Certified |
| 3 | Fatehpur | Teliyani | Jagannathpur | 427744 | Kasimpur | 66 | 66 | 100 | Har Gar Jal | Not Certified |