Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Deoria | LC INFRA | 8361278 | BANARHI G.P. WATER SUPPLY SCHEME | 237.24 | 93.01 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 25 | 25 | NA | 0 | NA | No | 11567.00 | 7500.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Deoria | Salempur | BANARHI | 460425 | Banarhi | 182 | 182 | 100 | Har Gar Jal | Not Certified | 
| 2 | Deoria | Salempur | BANARHI | 460426 | Dubouli | 79 | 75 | 95 | Work In Progress | Not Certified | 
| 3 | Deoria | Salempur | BANARHI | 460427 | Bhiswa | 14 | 14 | 100 | Har Gar Jal | Not Certified | 
| 4 | Deoria | Salempur | BANARHI | 460428 | Gardah Srikant | 4 | 1 | 25 | Work In Progress | Not Certified | 
| 5 | Deoria | Salempur | BANARHI | 680832 | Bharouli | 220 | 220 | 100 | Har Gar Jal | Not Certified |