Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Bareilly | NCC Ltd. | 8361424 | LAHIYA | 346.56 | 188.08 | view more | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 19 | 19 | Yes | 0 | NA | No | 10180.00 | 10180.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bareilly | Bithiri Chainpur | Lahiya | 403721 | Lahiya | 414 | 414 | 100 | Har Gar Jal | Certified | 
| 2 | Bareilly | Bithiri Chainpur | Lahiya | 403722 | Nawada Brahmnan | 84 | 84 | 100 | Har Gar Jal | Certified | 
| 3 | Bareilly | Bithiri Chainpur | Lahiya | 403723 | Rasoola Gulam Abbas | 78 | 78 | 100 | Har Gar Jal | Certified |