Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Bareilly | NCC Ltd. | 8361455 | JHADA | 329.37 | 174.37 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Bareilly | Faridpur | Jhada | 404394 | Jhada | 212 | 212 | 100 | Har Gar Jal | Certified | Verified |
2 | Bareilly | Faridpur | Jhada | 404395 | Lakhanpur | 105 | 105 | 100 | Har Gar Jal | Certified | Verified |
3 | Bareilly | Faridpur | Jhada | 404396 | Unchasia | 256 | 256 | 100 | Har Gar Jal | Certified | Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 19 | 19 | Yes | 0 | NA | No | 12518.00 | 12518.00 |