Scheme Details
DISTRICT
Deoria
AGENCY
LC INFRA
SCHEME ID
8361749
SCHEME NAME
KISHORI CHHAPAR GP WATER SUPPLY SCHEME
ESTIMATED COST
255.18
EXPENDITURE
146.57
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
24
Procured
24
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
8683.00
Meter
Length Laid
8600.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Deoria | Baitalpur | Baitalpur | 459332 | Baitalpur | 469 | 467 | 100% | Work In Progress | Not Certified |
| 2 | Deoria | Bankata | Kishori Chhapar | 460879 | Kishori Chhapar | 149 | 149 | 100% | Har Ghar Jal | Not Certified |
| 3 | Deoria | Bankata | Kishori Chhapar | 460880 | Nainha | 78 | 78 | 100% | Har Ghar Jal | Not Certified |
| 4 | Deoria | Bankata | Kishori Chhapar | 460881 | Bhatwalia Bhat | 54 | 54 | 100% | Har Ghar Jal | Not Certified |