| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Raebareli | NCC Ltd. | 8361805 | LOHANIPUR | 438.53 | 183.01 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 35 | 35 | Yes | 0 | NA | No | 8382.00 | 7937.34 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Raebareli | Harchandpur | Lohanipur | 416591 | Lohanipur | 465 | 446 | 96 | Work In Progress | Not Certified | 
| 2 | Raebareli | Harchandpur | Lohanipur | 416592 | Maidanpur | 180 | 178 | 99 | Work In Progress | Not Certified | 
| 3 | Raebareli | Harchandpur | Lohanipur | 416593 | Paltu Tanda | 80 | 75 | 94 | Work In Progress | Not Certified |