Scheme Details
DISTRICT
Chandauli
AGENCY
VSA
SCHEME ID
8361953
SCHEME NAME
BASUNI
ESTIMATED COST
529.39
EXPENDITURE
203.59
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
42
Procured
42
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
12125.00
Meter
Length Laid
13969.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Chandauli | Sakaldiha | Dhoos Khas | 474511 | Basaratiya | 113 | 113 | 100% | Har Ghar Jal | Certified |
| 2 | Chandauli | Sakaldiha | Basani | 474527 | Basani | 568 | 568 | 100% | Har Ghar Jal | Certified |
| 3 | Chandauli | Chahaniya | Papaura | 656864 | BAJIDPUR | 45 | 0 | 0% | Work In Progress | Not Certified |