| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Deoria | LC INFRA | 8362033 | CHAKARA UPADHYAY GP WATER SUPPLY SCHEME | 235.71 | 109.44 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 19 | 19 | Yes | 0 | NA | No | 9500.00 | 7500.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Deoria | Bhagalpur | Chakara Upadhyay | 460253 | Chakara Upadhyay | 141 | 141 | 100 | Har Gar Jal | Not Certified |
| 2 | Deoria | Bhagalpur | Chakara Upadhyay | 460254 | Chakara Nonar | 54 | 54 | 100 | Har Gar Jal | Not Certified |
| 3 | Deoria | Bhagalpur | Chakara Upadhyay | 460255 | Kardoundi | 134 | 134 | 100 | Har Gar Jal | Not Certified |