Scheme Details
DISTRICT
Raebareli
AGENCY
NCC Ltd.
SCHEME ID
8362389
SCHEME NAME
KUNDAULI
ESTIMATED COST
418.74
EXPENDITURE
345.03
AUTOMATION STATUS
Disconnected
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
28
Procured
28
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
18190.00
Meter
Length Laid
18055.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Raebareli | Bachhraon | Kundauli | 416218 | Kundauli | 573 | 573 | 100% | Har Ghar Jal | Certified |