Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Varanasi | Larsen & Toubro Ltd | 8362437 | SULTANIPUR | 200.78 | 90.83 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 11 | 11 | Yes | 0 | NA | No | 6102.00 | 6013.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Varanasi | Cholapur | Sultanipur | 475902 | Puraram Jee | 22 | 22 | 100 | Har Gar Jal | Certified |
| 2 | Varanasi | Cholapur | Sultanipur | 475903 | Sultanipur | 189 | 189 | 100 | Har Gar Jal | Certified |