Scheme Details
DISTRICT
Raebareli
AGENCY
NCC Ltd.
SCHEME ID
8362499
SCHEME NAME
SULTANPUR
ESTIMATED COST
369.00
EXPENDITURE
288.13
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
13
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
21
Procured
21
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
12083.00
Meter
Length Laid
11745.03
Meter
Scheme Assigned Villages
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Raebareli | Maharajganj | Sultanpur | 416346 | Sultanpur | 372 | 364 | 98% | Work In Progress | Not Certified |
| 2 | Raebareli | Maharajganj | Sultanpur | 416347 | Balai Mau | 86 | 79 | 92% | Work In Progress | Not Certified |
| 3 | Raebareli | Maharajganj | Sultanpur | 416348 | Hajipur | 42 | 21 | 50% | Work In Progress | Not Certified |
| 4 | Raebareli | Maharajganj | Sultanpur | 416349 | Chilauli | 19 | 18 | 95% | Work In Progress | Not Certified |