Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Prayagraj | Larsen & Toubro Ltd | 8362648 | BTAJUDDINPUR GRAM PANCHAYAT MULTI VILLAGESWATER SUPLY SCHEME | 268.87 | 61.13 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 25 | 25 | No | 0 | NA | No | 11001.00 | 11001.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Prayagraj | Soraon | Tajuddinpur | 432016 | Tajuddinpur | 194 | 185 | 95 | Work In Progress | Not Certified | 
| 2 | Prayagraj | Soraon | Tajuddinpur | 432017 | Babhanpur Dera Gadai | 7 | 1 | 14 | Work In Progress | Not Certified | 
| 3 | Prayagraj | Soraon | Tajuddinpur | 432018 | Nasirpur Naherpur | 136 | 109 | 80 | Work In Progress | Not Certified |