Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | NCC Ltd. | 8362878 | PARSA URF AGLAGAWA WATER SUPPLY SCHEME | 313.53 | 330.42 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 22 | 22 | Yes | 0 | NA | No | 11197.00 | 11258.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Gola | Parsa Urf Aglagawa | 457191 | Parsa Urf Aglagawa | 211 | 211 | 100 | Har Gar Jal | Certified |
| 2 | Gorakhpur | Gola | Parsa Urf Aglagawa | 457192 | Mishrauli | 67 | 67 | 100 | Har Gar Jal | Certified |