Scheme Details
DISTRICT
Etah
AGENCY
Power Mech Projects Ltd
SCHEME ID
8363940
SCHEME NAME
GARHWALA
ESTIMATED COST
388.98
EXPENDITURE
201.10
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
1
Work Started
0
Work Completed
1
Solar Plant
Required
46
Procured
46
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
8869.00
Meter
Length Laid
9999.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
5 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Etah | Nidhauli Kalan | Garhwala | 399450 | Garhwala | 651 | 651 | 100% | Har Ghar Jal | Certified |
| 2 | Etah | Nidhauli Kalan | Manaura | 399466 | Manaura | 887 | 874 | 99% | Work In Progress | Not Certified |
| 3 | Etah | Nidhauli Kalan | Gurha | 399467 | Gurha | 182 | 180 | 99% | Work In Progress | Not Certified |
| 4 | Etah | Nidhauli Kalan | Nagla Bari | 399500 | Bagla Bari | 256 | 246 | 96% | Work In Progress | Not Certified |
| 5 | Etah | Nidhauli Kalan | Bhadbas | 399528 | Bhadbas | 587 | 584 | 99% | Work In Progress | Not Certified |