Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Azamgarh LC INFRA 8388631 GUJARPAR 704.02 226.32 Not Integrated

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
3 2 2 2 2 1 1 0 58 58 Yes 0 NA No 24094.00 17745.00

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Azamgarh Sathiyaon Gujarpar 463079 Gujarpar 1015 1015 100 Har Gar Jal Certified
2 Azamgarh Sathiyaon Gujarpar 463080 Bada Gaon 70 70 100 Har Gar Jal Certified
3 Azamgarh Sathiyaon Gujarpar 463081 Basaratpur 4 4 100 Har Gar Jal Certified