Scheme Details
DISTRICT
Etah
AGENCY
Power Mech Projects Ltd
SCHEME ID
8389105
SCHEME NAME
Arhapura
ESTIMATED COST
228.03
EXPENDITURE
117.60
AUTOMATION STATUS
Disconnected
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
1
Solar Plant
Required
25
Procured
25
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
10223.00
Meter
Length Laid
10929.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Etah | Nidhauli Kalan | Arha Pura | 399440 | Arha Pura | 488 | 487 | 100% | Work In Progress | Not Certified |