Scheme Details
DISTRICT
Pilibhit
AGENCY
PNC-SPML-JV
SCHEME ID
8389916
SCHEME NAME
ARJUNPUR MUSTQIL
ESTIMATED COST
216.29
EXPENDITURE
125.72
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
16
Procured
16
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
4905.00
Meter
Length Laid
4905.00
Meter
Scheme Assigned Villages
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Pilibhit | Bisalpur | Arjunpur Must. | 405259 | Arjunpur Must. | 229 | 222 | 97% | Work In Progress | Not Certified |
| 2 | Pilibhit | Bisalpur | Arjunpur Must. | 405260 | Hirapur Diyuhi Must. | 99 | 98 | 99% | Work In Progress | Not Certified |