S.No. Project Name District Scheme Sanctioned Cost Civil Work E&M Work Project Preparation Project Supervision GST Power Connection With GST ESAMP Communication & Public Outreach Governance & Accountability Plan Others CAPEX Total O&M Cost - 15 Years Electricity / Fuel Charges With GST OPEX Total Grand Total Project Status Remarks Last Updated Date
1 Balance Darins Tapping and Augmentation of SPSs at Agra City Agra NGP 126.41 - - - - - - - - - - - - - - 0.00 Ongoing - -
2 Tapping of newly Identified Drains falling in River Varuna in Varanasi Under Namami Gange Programme Varanasi NGP2-NON EAP 174.98 - - - - - - - - - - - - - - 0.00 Tendering - -
3 Interception & Diversion Of 14 Untapped Drains Of Kanpur City (Along with Supplementary Works) Kanpur Nagar NGP2-NON EAP 138.11 - - - - - - - - - - - - - - 0.00 Ongoing - -
4 Interception and Diversion of Drains/Nala Falling in Varuna River and STP for Bhadohi Town Sant Ravidas Nagar NGP2-NON EAP 127.26 - - - - - - - - - - - - - - 0.00 Ongoing - -
5 Faecal Sludge Management for Pollution abatement of river Ganga at Manikpur, Pratapgarh Pratapgarh Non EAP 8.56 - - - - - - - - - - - - - - 0.00 Ongoing - -
6 DPR OF 08 KLD Fecal Sludge Treatment Plant At Dalmau Raibareli Rae Bareli NMCG 4.40 - - - - - - - - - - - - - - 0.00 Ongoing - -
7 Gulaothi I&D works Bulandshahr NMCG 50.98 - - - - - - - - - - - - - - 0.00 Ongoing - -
8 I&D and STP Work in Deobandh Saharanpur NGP 134.71 - - - - - - - - - - - - - - 0.00 Ongoing - -
9 Pollution Abatement of Gomti River (Phase-II, Part-II ) Lucknow Lucknow NGP 351.03 - - - - - - - - - - - - - - 0.00 Ongoing - -
10 Interception, Diversion of Balance discharge of 02 drains and 50 MLD STP to Augment existing Treatment Capacity (80 MLD) Naini STP for Sewerage District-A at Prayagraj Uttar Pradesh under DBOT mode PrayagRaj NGP 186.47 - - - - - - - - - - - - - - 0.00 Ongoing - -
11 I&D and STP works at District-Hapur Hapur NGP 49.06 - - - - - - - - - - - - - - 0.00 Ongoing - -
12 I&D and STP Work in Bantikhera and Babri village, Shamli Shamli NGP 55.47 - - - - - - - - - - - - - - 0.00 Ongoing - -
13 I&D and STP Work in Thanabhawan, Shamli Shamli NGP 97.19 - - - - - - - - - - - - - - 0.00 Ongoing - -
14 I&D and STP Work in Shamli Shamli NGP 206.02 - - - - - - - - - - - - - - 0.00 Ongoing - -
15 I&D and STP Work in Banat, Shamli Shamli NGP 48.71 - - - - - - - - - - - - - - 0.00 Ongoing - -
16 Interception, Diversion of Balance 13 drains and Augmentation of Salori STP capacity by 43 MLD (Sewerage District-C) at Prayagraj Uttar Pradesh under DBOT mode PrayagRaj NGP 331.75 - - - - - - - - - - - - - - 0.00 Ongoing - -
17 I&D and STP works at Hathras Town Hathras NGP 128.90 - - - - - - - - - - - - - - 0.00 Ongoing - -
18 Pollution Abatement of Gomti River (Phase-II, Part-I) Lucknow Lucknow NGP 264.67 - - - - - - - - - - - - - - 0.00 Ongoing - -
19 Interception, Diversion of Balance 7 drains and Augmentation of Rajapur STP capacity by 90 MLD (Sewerage District-D) at Prayagraj Uttar Pradesh under DBOT mode PrayagRaj NGP 475.98 - - - - - - - - - - - - - - 0.00 Ongoing - -
20 I&D and 13 MLD STP works at Vrindavan City Mathura NGP 77.70 - - - - - - - - - - - - - - 0.00 Ongoing - -
21 I&D and STP works at Kosi Kalan Town, District Mathura Mathura NGP 66.56 - - - - - - - - - - - - - - 0.00 Ongoing - -
22 Chhata Town Sewerage Scheme (I&D and STP works), District Mathura Mathura NGP 56.15 - - - - - - - - - - - - - - 0.00 Ongoing - -
23 I&D and Treatment works for Assi-BHU Area (Phase-II), Varanasi Varanasi NGP 308.09 - - - - - - - - - - - - - - 0.00 Completed - -
24 I&D and STP Work in Kairana Shamli CGF 78.42 - - - - - - - - - - - - - - 0.00 Completed - -
25 Pollution Abatement Of Gomti River (Phase 1 Part 1) Lucknow Lucknow NGP 240.93 - - - - - - - - - - - - - - 0.00 Ongoing - -
26 I&D and STP works at Bagpat Baghpat NGP 77.36 - - - - - - - - - - - - - - 0.00 Completed - -
27 Firozabad Sewerage Scheme ( Interception & Diversion Works) Distt Firozabad Firozabad NGP1-NON EAP 51.08 - - - - - - - - - - - - - - 0.00 Completed - -
28 Faecal Sludge Management for abatement of pollution in River Ganga at Chunar, Mirzapur, U.P. Mirzapur NGP 2.70 - - - - - - - - - - - - - - 0.00 Completed - -
29 Etawah Sewerage Scheme ( Interception & Diversion Works) DIstt- Etawah Etawah NGP1-NON EAP 140.60 - - - - - - - - - - - - - - 0.00 Completed - -
30 Interception & Diversion (I&D) of drains and Sewerage Treatment Plant at Kasganj Kasganj NGP1-NON EAP 76.73 - - - - - - - - - - - - - - 0.00 Completed - -
31 I&D of Drains and Sewerage Treatment Plant works with 15 Years O&M at Sultanpur Sultanpur NGP 70.18 - - - - - - - - - - - - - - 0.00 Completed - -
32 Interception & Diversion (I&D) of Drains and Sewerage Treatment Plant at Jaunpur , U.P. Jaunpur NGP 206.05 - - - - - - - - - - - - - - 0.00 Completed - -
33 I&D of Drains at Ayodhya-Ayodhya. DBOT, NGP Ayodhya NGP 37.67 - - - - - - - - - - - - - - 0.00 Completed - -
34 Rehabilitation of Sewerage Infrastructure and Augmentation/upgradation of STP at Vrindavan Mathura NGP1-NON EAP 42.82 - - - - - - - - - - - - - - 0.00 Completed - -
35 Interception, Diversion of Drains & Sewage Treatment Works at Ramnagar, Dist. Varanasi Varanasi NGP 72.91 - - - - - - - - - - - - - - 0.00 Completed - -
36 I and D of Sisamau and 5 other drains Kanpur Nagar NGP 63.80 - - - - - - - - - - - - - - 0.00 Completed - -
37 Sewerage Works in Sewerage Dist 1 Kanpur Kanpur Nagar NGP 430.49 - - - - - - - - - - - - - - 0.00 Completed - -
38 Kannauj Sewerage Scheme Phase II Kannauj Non EAP 43.66 - - - - - - - - - - - - - - 0.00 Completed - -
39 JICA Assisted Ganga Action Plan (GAP) Phase-II, Varanasi Varanasi NGP 659.62 - - - - - - - - - - - - - - 0.00 Completed - -
40 Interception Diversion and Treatment works at Bithoor Town Kanpur Kanpur Nagar NGP 13.40 - - - - - - - - - - - - - - 0.00 Completed - -
41 Prevention of Pollution of River Ramganga at Moradabad Moradabad Non EAP 330.05 - - - - - - - - - - - - - - 0.00 Completed - -
42 Narora Sewerage Scheme Bulandshahr EAP 48.45 - - - - - - - - - - - - - - 0.00 Completed - -
43 Anupshahar Sewerage Scheme Bulandshahr EAP 75.79 - - - - - - - - - - - - - - 0.00 Completed - -
44 Garhmukteshwar Sewerage Scheme. Hapur Non EAP 46.51 - - - - - - - - - - - - - - 0.00 Completed - -
45 Sewer Network in District E of Allahabad Part-II PrayagRaj NGRBA EAP 52.78 - - - - - - - - - - - - - - 0.00 Completed - -
46 Sewerage Scheme for District B PrayagRaj NGRBA EAP 300.84 - - - - - - - - - - - - - - 0.00 Completed - -
47 Sewerage Scheme for District A PrayagRaj NGRBA EAP 299.39 - - - - - - - - - - - - - - 0.00 Completed - -
48 14 MLD Capacity STP at Salori Allahabad PrayagRaj NGRBA EAP 42.40 - - - - - - - - - - - - - - 0.00 Completed - -
49 Sewerage Scheme for District C PrayagRaj NGRBA EAP 170.95 - - - - - - - - - - - - - - 0.00 Completed - -
50 Sewerage work in Sewerage District E of Allahabad PrayagRaj NGRBA EAP 142.00 - - - - - - - - - - - - - - 0.00 Completed - -
51 Sewerage and Non Sewerage Schemes for Pollution abatement of River Ganga at Allahabad District B&EU.P PrayagRaj Non EAP 305.34 - - - - - - - - - - - - - - 0.00 Completed - -