Sr.No. | Components | Target | Achivement | % |
---|---|---|---|---|
1 | 2 | 3 | 4 | 5 |
1 | Tubewell | 592 | 583 | 98.48 |
2 | Pump House | 592 | 557 | 94.09 |
3 | Chlorination system | 279 | 255 | 91.40 |
4 | OHT | 471 | 463/261 | 98.30 |
5 | Distribution (Line Laying in Km.) | 4386 | 4279 | 97.56 |
6 | Solar Plant | 431 | 324 | 75.17 |
7 | F.H.T.C. | 266920 | 243934 | 91.39 |
9 | ROAD DISMENTLING/RESTORATION(KM) | 1570 | 1518 | 96.69 |
10 | Villages where 100 % road restoration completed | 97064 | 59914 | 61.73 |
11 | Comissioning of Village | 764 | 405 | 53.01 |
12 | Regular water supply | 764 | 400 | 52.36 |
Sr.No. | Agency | No Of Scheme | No Of Village | households | FHTC | FHTC % | Har Gar Gal | Certified |
---|---|---|---|---|---|---|---|---|
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 |
1 | ION EXCHANGE | 29 | 47 | 16764 | 14720 | 87.81% | 22 | 2 |
2 | JMC - Lakshmi (JV) | 143 | 206 | 56325 | 51846 | 92.05% | 61 | 26 |
3 | Power Mech Projects Ltd | 316 | 511 | 157679 | 142716 | 90.51% | 206 | 31 |
Total | 488 | 764 | 230768 | 209282 | 90.69% | 289 | 59 |