Jal Jeevan Mission-Agency Dashboard

Heirarchy Details
Assign District:
Assign Scheme :
Assign Villages :
Physical Progress
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Certified :
HO Villages :
Incoming Complaints Received
All Complaints :
Close Complaints :
Pending Complaints :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Detaile(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Agency Progress Details
Sr.No. District No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 Bijnor 606 1311 307348 279452 90.92% 692 91
Components Wise Physical Progress
Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 612 611 99.84
2 Pump House 612 609 99.51
3 Chlorination system 485 441 90.93
4 OHT 598 596/192 99.67
5 Distribution (Line Laying in Km.) 5467 5101 93.31
6 Solar Plant 601 582 96.84
7 F.H.T.C. 306935 279039 90.91
8 W.T.P.
9 ROAD DISMENTLING/RESTORATION(KM) 1666 1649 98.98
10 Villages where 100 % road restoration completed 97065 58910 60.69
11 Comissioning of Village 1311 1038 79.18
12 Regular water supply 1311 1035 78.95