Sr.No. Name of Sewerage Project Scheeme Type Mode of Project AA&ES and date No. of STP STP Capacity No.Of Drains Agency Name Agreement Cost Date of Comp. As per Agreement Date of Start Expected Date of Completion. Previus progress Current progress Weekly progress Critical Issu Remark
Date of Sanction Sanction cost work Cost Centage O & M Cost Physical Progress Financial Progress Physical Progress Financial Progress Physical Progress Financial Progress(CR)
Total -- 4255.74 1796.87 134.06 2328.27 36 661.30 170 -- 3337.91 -- -- -- 1302.81 1356.48 1308.44 1356.48 5.63 0.00 -- --
1 Agra Sewerage Scheme( Interception & diversion and STP works) NGP2-EAP HAM 06-May-2020 842.25 371.29 25.40 445.56 13 177.60 26 M/s AWWMPL Pvt Ltd 582.84 04-Apr-2025 05-Apr-2023 04-Apr-2025 38.99 67.83 39.23 67.83 0.24 0.00 work in progress
2 Development of Sewage Treatment Plant at Bareilly NGP HAM 03-Jan-2019 271.39 139.44 10.70 121.25 3 63.00 15 M/s EIEPL Bareilly Infra Engineers Ltd 233.72 30-Aug-2024 31-Aug-2022 30-Aug-2024 99.00 207.32 99.00 207.32 0.00 0.00 All 03 nos. of STP of 20mld, 1mld and 42 mld have been completed on 23.03.2024. Plants are under trial run.
3 I&D and STP Work in Budhana Town Non EAP HAM 18-Feb-2019 48.76 25.10 1.70 21.96 1 10.00 3 M/S Muzaffarnagar STP Pvt Ltd 41.28 03-Jun-2023 04-Jun-2021 31-Oct-2023 100.00 29.15 100.00 29.15 0.00 0.00 All 03 I&D and 10 MLD STP work completed. STP commissioned on 27.06.2023, Trial & Run in Progress.
4 I&D and STP Work in Kairana NGP DBOT 07-Dec-2020 78.42 37.28 2.63 38.51 1 15.00 1 M/s SIPL RKC JV 59.19 27-May-2023 28-Aug-2021 30-Apr-2024 93.42 29.58 97.47 29.58 4.05 0.00 I&D work completed, STP commissioned by Manual Mode on 12 February, 2024, Electrical/Mechanical instrument installation work and finishing work in progress.
5 I&D and STP Work in Muzaffarnagar NGP HAM 02-Jan-2019 78.42 37.28 2.63 38.51 2 54.50 5 M/S Muzaffarnagar STP Pvt Ltd 205.09 03-Jun-2023 04-Jun-2021 31-May-2024 93.46 141.79 93.46 141.79 0.00 0.00 22 MLD STP Sahawali: Commissioned on 07.06.2023. 32.5 MLD Kidwai Nagar: 02 Nos. I&D work completed, STP commissioned by Manual Mode by two I&D on dated 18 February, 2024, E&M Instrument installation a
6 I&D and STP works at Farrukhabad-Fatehgarh NGP HAM 09-Feb-2021 261.12 188.71 6.98 72.41 2 47.70 8 M/S HNB Engineers Private Ltd. 252.41 27-Jun-2024 28-Jun-2023 27-Jun-2024 84.90 179.04 84.90 179.04 0.00 0.00 Construction of STP has been completed. Electro Mechanical works of STP and associated I and D works is in progress.
7 I&D and STP works at Kanpur-Pankha NGP HAM 12-Mar-2018 967.23 248.39 31.05 718.84 1 30.00 2 M/s Kanpur River Management Pvt. Ltd. 708.70 25-Oct-2021 11-Oct-2019 31-Oct-2023 99.00 258.27 99.00 258.27 0.00 0.00 30 MLD Panka STP has been commissioned. Works of Sludge handling Unit and OCEMS are to be completed.
8 I&D and Treatment works for Assi-BHU Area (Phase-II), Varanasi NGP DBOT 19-Oct-2022 308.09 97.62 7.81 172.94 1 55.00 2 M/s Enviro Infra Engineers limited MTS JV 151.55 06-Dec-2025 07-Mar-2024 06-Dec-2025 2.50 4.23 2.50 4.23 0.00 0.00 Letter of award given to M/s Enviro Infra Engineers Limited MTS JV, 201, 2nd Floor, RG Metro Arcade, Rohini Sector II, Delhi- 110085 on 06-11-2023. Agreement is signed and Date of start is 07.03.24
9 I&D of Drains and Sewerage Treatment Plant works with 15 Years O&M at Sultanpur NGP DBOT 24-Dec-2018 64.76 36.50 2.59 23.91 2 7.00 4 M/s EIEPL- ABI(JV) 60.41 29-May-2022 30-Nov-2019 30-Apr-2024 99.82 44.04 99.82 44.04 0.00 0.00 Trail and Run of 10 MLD STP (Vinobapuri) ,5 MLD STP (Palhipur) & 02 MLD STP(Karaudiya) has been started
10 I&D of Drains and STP works in Shuklaganj (05MLD) NGP HAM 28-Jul-2017 65.18 25.93 1.90 37.35 1 5.00 5 M/s KRMPL Kanpur 38.87 10-Jul-2021 11-Oct-2019 31-Dec-2023 81.00 23.47 81.00 23.47 0.00 0.00 There are only 15-20 manpower has been engaged in Centrifuge, Manhole, PTU and I&D work. No any manpower deployed in Electrical & Mechanical works from last 6 months. Progress of work is very poor.
11 I&D of Drains and STP works in Unnao (15MLD) NGP HAM 28-Jul-2017 102.20 43.73 3.22 55.25 1 15.00 1 M/s KRMPL Kanpur 68.68 10-Jul-2021 11-Oct-2019 31-Oct-2023 95.50 52.01 95.50 52.01 0.00 0.00 Cleaning of 700 mt. sewer line is balance till date and only 10 No. manpower has been deployed from last 4-5 days. STP 4-6 Hrs operating daily from 07.11.2023 through temporary line.
12 Interception & Diversion (I&D) of Drains and Sewerage Treatment Plant at Moradabad zone 2 NGP HAM 23-Jul-2018 118.69 53.53 3.52 61.64 1 25.00 5 Moradabad STP Pvt Ltd 113.85 19-Jan-2025 20-Jan-2023 19-Jan-2025 54.00 10.46 55.00 10.46 1.00 0.00 Effective date of start 20.01.2023 and project completion date 19.01.2025. 25 MLD STP progress 55%, MPS 40 MLD progress 18%, Sewer line 3.40 km. Staff Quarter 95%, and over all project progress 55%
13 Interception & Diversion and STP at Mirzapur, U.P. NGP HAM 28-May-2020 129.08 50.50 4.04 73.06 2 17.00 18 M/s Mirzapur Ghazipur STPs Private Limited 151.58 09-Jan-2024 10-Apr-2022 30-Apr-2024 99.00 74.36 99.00 74.36 0.00 0.00 Rehabilitation of 14 MLD UASB STP completed. Approval for cost of Power Connection received from NMCG on 04.03.3023. Work in Progress. Permission for effluent discharge yet to be received from Irrigat
14 Interception, Diversion of Balance 13 drains and Augmentation of Salori STP capacity by 43 MLD (Sewerage District-C) at Prayagraj Uttar Pradesh under DBOT mode NGP DBOT 14-Mar-2023 331.75 180.27 11.22 140.27 1 43.00 13 M/s HNB Private ltd. - M/s Tirupati Cements Products (JV) 204.40 18-Aug-2025 19-Mar-2024 0.00 0.00 0.00 0.00 0.00 0.00 Contract Agreement has been formed and Date of start 19.03.2024 and Date of Completion 18.08.2025 has been given to firm. Survey work has been started
15 Pollution Abatement Of Gomti River (Phase 1 Part 1) Lucknow NGP DBOT 06-May-2020 213.91 101.31 6.97 105.63 2 42.50 5 M/s R.K. Engineers- Khilari Infrastructure (JV) 174.93 30-Nov-2023 01-Jun-2022 31-May-2024 78.77 90.44 79.11 90.44 0.34 0.00 Work of 39 MLD Daulatganj STP is in progress. Principal approval of 3.5 MLD Barikala STP has been given by NMCG on dt. 09.06.2023 but financial approval for same is still awaited.
16 Pollution Abatement Works for River Saryu/Ghaghara at Faizabad town, District-Ayodhya (Interception & Diversion of Drains with 33 MLD STP) NGP HAM 06-May-2021 221.66 109.03 7.62 105.01 1 33.00 15 M/s Eco Protection Engineer Pvt Ltd 149.47 02-Jan-2025 03-Mar-2023 15-May-2024 84.95 76.75 84.95 76.75 0.00 0.00 All 4 SBR unit has been hydro-tested and 80% air pipeline is completed. Raft of MPS unit is casted and partition wall work is under progress. Finishing and land scaping work is in progress. NOC for tr
17 Sewerage, Sewage Treatment & Disposal for Ghazipur, U.P. NGP HAM 06-May-2020 152.83 50.96 4.08 96.17 1 21.00 42 M/s Mirzapur Ghazipur STPs Private Limited 140.94 09-Jan-2024 10-Apr-2022 30-Apr-2024 98.50 67.74 98.50 67.74 0.00 0.00 Proposal for additional cost implication is approved by NMCG in 54th EC meeting and letter issued on 29.02.2023. Work in Progress