Jal Jeevan Mission-Agency Dashboard

Heirarchy Details
Assign District:
Assign Scheme :
Assign Villages :
Physical Progress
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Certified :
HO Villages :
Incoming Complaints Received
All Complaints :
Close Complaints :
Pending Complaints :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Detaile(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Agency Progress Details
Sr.No. District No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 Rampur 246 487 126455 118483 93.70% 190 93
Components Wise Physical Progress
Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 260 256 98.46
2 Pump House 260 243 93.46
3 Chlorination system 154 149 96.75
4 OHT 252 248/72 98.41
5 Distribution (Line Laying in Km.) 2130 2052 96.34
6 Solar Plant 232 192 82.76
7 F.H.T.C. 125930 117959 93.67
8 W.T.P.
9 ROAD DISMENTLING/RESTORATION(KM) 1445 1422 98.41
10 Villages where 100 % road restoration completed 97065 58910 60.69
11 Comissioning of Village 487 377 77.41
12 Regular water supply 487 294 60.37