Physical Progress
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Certified :
HO Villages :
Incoming Complaints Received
All Complaints :
Close Complaints :
Pending Complaints :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Detaile(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Agency Progress Details
Sr.No. District No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 Rampur 179 296 82363 78425 95.22% 153 104
Components Wise Physical Progress
Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 179 179 100.00
2 Pump House 179 157 87.71
3 Chlorination system 107 104 97.20
4 OHT 177 177/117 100.00
5 Distribution (Line Laying in Km.) 1188 1135 95.54
6 Solar Plant 137 106 77.37
7 F.H.T.C. 82363 78425 95.22
8 W.T.P.
9 ROAD DISMENTLING/RESTORATION(KM) 902 876 97.12
10 Villages where 100 % road restoration completed 97065 58910 60.69
11 Comissioning of Village 296 166 56.08