Jal Jeevan Mission-Agency Dashboard

Heirarchy Details
Assign District:
Assign Scheme :
Assign Villages :
Physical Progress
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Certified :
HO Villages :
Incoming Complaints Received
All Complaints :
Close Complaints :
Pending Complaints :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Detaile(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Agency Progress Details
Sr.No. District No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 Meerut 332 472 228818 218147 95.34% 282 232
Components Wise Physical Progress
Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 340 333 97.94
2 Pump House 340 334 98.24
3 Chlorination system 302 301 99.67
4 OHT 309 305/295 98.71
5 Distribution (Line Laying in Km.) 3025 2934 96.99
6 Solar Plant 264 253 95.83
7 F.H.T.C. 228818 218147 95.34
8 W.T.P.
9 ROAD DISMENTLING/RESTORATION(KM) 2417 2396 99.13
10 Villages where 100 % road restoration completed 97065 58910 60.69
11 Comissioning of Village 472 428 90.68
12 Regular water supply 472 427 90.47