Jal Jeevan Mission-Agency Dashboard

Heirarchy Details
Assign District:
Assign Scheme :
Assign Villages :
Physical Progress
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Certified :
HO Villages :
Incoming Complaints Received
All Complaints :
Close Complaints :
Pending Complaints :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Detaile(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Agency Progress Details
Sr.No. District No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 Bareilly 876 1807 481301 476425 98.99% 1618 342
Components Wise Physical Progress
Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 892 891 99.89
2 Pump House 892 879 98.54
3 Chlorination system 804 552 68.66
4 OHT 877 875/390 99.77
5 Distribution (Line Laying in Km.) 8629 8328 96.51
6 Solar Plant 850 821 96.59
7 F.H.T.C. 481138 476262 98.99
8 W.T.P. 0 0 0.00
9 ROAD DISMENTLING/RESTORATION(KM) 4205 4108 97.69
10 Villages where 100 % road restoration completed 97064 59914 61.73
11 Comissioning of Village 1807 1201 66.46
12 Regular water supply 1807 1180 65.30