Jal Jeevan Mission-Agency Dashboard

Heirarchy Details
Assign District:
Assign Scheme :
Assign Villages :
Physical Progress
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Certified :
HO Villages :
Incoming Complaints Received
All Complaints :
Close Complaints :
Pending Complaints :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Detaile(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Agency Progress Details
Sr.No. District No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 Rae Bareli 211 360 102644 96144 93.67% 196 101
Components Wise Physical Progress
Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 236 231 97.88
2 Pump House 236 223 94.49
3 Chlorination system 157 152 96.82
4 OHT 214 211/66 98.60
5 Distribution (Line Laying in Km.) 3408 3307 97.04
6 Solar Plant 210 210 100.00
7 F.H.T.C. 102644 96144 93.67
8 W.T.P.
9 ROAD DISMENTLING/RESTORATION(KM) 647 632 97.68
10 Villages where 100 % road restoration completed 97065 58917 60.70
11 Comissioning of Village 360 218 60.56
12 Regular water supply 360 214 59.44