Physical Progress
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Certified :
HO Villages :
Incoming Complaints Received
All Complaints :
Close Complaints :
Pending Complaints :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Detaile(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Agency Progress Details
Sr.No. District No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 Etawah 259 381 140330 131323 93.58% 37 4
Components Wise Physical Progress
Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 290 290 100.00
2 Pump House 290 266 91.72
3 Chlorination system 73 59 80.82
4 OHT 251 250/49 99.60
5 Distribution (Line Laying in Km.) 2996 2879 96.09
6 Solar Plant 245 241 98.37
7 F.H.T.C. 140330 131323 93.58
8 W.T.P. 0 0 0.00
9 ROAD DISMENTLING/RESTORATION(KM) 997 974 97.69
10 Villages where 100 % road restoration completed 97064 59914 61.73
11 Comissioning of Village 381 69 18.11
12 Regular water supply 381 56 14.70