Physical Progress
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Certified :
HO Villages :
Incoming Complaints Received
All Complaints :
Close Complaints :
Pending Complaints :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Detaile(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Agency Progress Details
Sr.No. District No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 Pratapgarh 456 1006 223096 208399 93.41% 523 35
Components Wise Physical Progress
Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 558 550 98.57
2 Pump House 558 543 97.31
3 Chlorination system 345 344 99.71
4 OHT 452 449/359 99.34
5 Distribution (Line Laying in Km.) 8514 8514 100.00
6 Solar Plant 440 440 100.00
7 F.H.T.C. 220245 205654 93.38
8 W.T.P.
9 ROAD DISMENTLING/RESTORATION(KM) 4104 4075 99.29
10 Villages where 100 % road restoration completed 97065 58955 60.74
11 Comissioning of Village 1006 303 30.12
12 Regular water supply 1006 129 12.82