Jal Jeevan Mission-Agency Dashboard

Heirarchy Details
Assign District:
Assign Scheme :
Assign Villages :
Physical Progress
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Certified :
HO Villages :
Incoming Complaints Received
All Complaints :
Close Complaints :
Pending Complaints :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Detaile(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Agency Progress Details
Sr.No. District No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 Gonda 142 296 68700 56057 81.60% 22 6
Components Wise Physical Progress
Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 146 141 96.58
2 Pump House 146 135 92.47
3 Chlorination system 64 42 65.63
4 OHT 142 135/10 95.07
5 Distribution (Line Laying in Km.) 2653 2147 80.93
6 Solar Plant 136 76 55.88
7 F.H.T.C. 68700 56057 81.60
8 W.T.P.
9 ROAD DISMENTLING/RESTORATION(KM) 336 328 97.62
10 Villages where 100 % road restoration completed 97065 58910 60.69
11 Comissioning of Village 296 106 35.81
12 Regular water supply 296 96 32.43