Jal Jeevan Mission-Agency Dashboard

Heirarchy Details
Assign District:
Assign Scheme :
Assign Villages :
Physical Progress
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Certified :
HO Villages :
Incoming Complaints Received
All Complaints :
Close Complaints :
Pending Complaints :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Detaile(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Agency Progress Details
Sr.No. District No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 Gonda 779 1254 341754 308889 90.38% 298 151
Components Wise Physical Progress
Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 771 724 93.90
2 Pump House 771 742 96.24
3 Chlorination system 301 283 94.02
4 OHT 759 758/197 99.87
5 Distribution (Line Laying in Km.) 11850 8098 68.34
6 Solar Plant 616 465 75.49
7 F.H.T.C. 340311 307453 90.34
8 W.T.P. 0 0 0.00
9 ROAD DISMENTLING/RESTORATION(KM) 682 670 98.24
10 Villages where 100 % road restoration completed 97064 59919 61.73
11 Comissioning of Village 1254 457 36.44
12 Regular water supply 1254 457 36.44