Jal Jeevan Mission-Agency Dashboard

Heirarchy Details
Assign District:
Assign Scheme :
Assign Villages :
Physical Progress
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Certified :
HO Villages :
Incoming Complaints Received
All Complaints :
Close Complaints :
Pending Complaints :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Detaile(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Agency Progress Details
Sr.No. District No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 Maharajganj 338 443 180986 171296 94.65% 108 39
Components Wise Physical Progress
Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 346 345 99.71
2 Pump House 346 339 97.98
3 Chlorination system 133 109 81.95
4 OHT 341 329/44 96.48
5 Distribution (Line Laying in Km.) 3277 3106 94.78
6 Solar Plant 227 225 99.12
7 F.H.T.C. 180986 171296 94.65
8 W.T.P.
9 ROAD DISMENTLING/RESTORATION(KM) 930 895 96.24
10 Villages where 100 % road restoration completed 97065 58910 60.69
11 Comissioning of Village 443 149 33.63
12 Regular water supply 443 105 23.70