Physical Progress
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Certified :
HO Villages :
Incoming Complaints Received
All Complaints :
Close Complaints :
Pending Complaints :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Detaile(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Agency Progress Details
Sr.No. District No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 Gorakhpur 628 1534 257934 251885 97.65% 1221 559
Components Wise Physical Progress
Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 636 637 100.00
2 Pump House 636 640 100.00
3 Chlorination system 620 564 90.97
4 OHT 629 629/463 100.00
5 Distribution (Line Laying in Km.) 6994 6937 99.19
6 Solar Plant 623 592 95.02
7 F.H.T.C. 257934 251885 97.65
8 W.T.P.
9 ROAD DISMENTLING/RESTORATION(KM) 2629 2542 96.69
10 Villages where 100 % road restoration completed 97065 58910 60.69
11 Comissioning of Village 1534 1129 73.60
12 Regular water supply 1534 1128 73.53