Physical Progress
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Certified :
HO Villages :
Incoming Complaints Received
All Complaints :
Close Complaints :
Pending Complaints :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Detaile(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Agency Progress Details
Sr.No. District No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 Kushi Nagar 454 910 337333 321408 95.28% 668 324
Components Wise Physical Progress
Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 454 454 100.00
2 Pump House 454 450 99.12
3 Chlorination system 426 354 83.10
4 OHT 454 451/226 99.34
5 Distribution (Line Laying in Km.) 6502 6155 94.66
6 Solar Plant 376 310 82.45
7 F.H.T.C. 334718 318794 95.24
8 W.T.P.
9 ROAD DISMENTLING/RESTORATION(KM) 1827 1797 98.36
10 Villages where 100 % road restoration completed 97065 58910 60.69
11 Comissioning of Village 913 608 66.59
12 Regular water supply 913 596 65.28