Jal Jeevan Mission-Agency Dashboard

Heirarchy Details
Assign District:
Assign Scheme :
Assign Villages :
Physical Progress
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Certified :
HO Villages :
Incoming Complaints Received
All Complaints :
Close Complaints :
Pending Complaints :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Detaile(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Agency Progress Details
Sr.No. District No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 Azamgarh 402 809 169013 155520 92.02% 190 123
Components Wise Physical Progress
Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 424 421 99.29
2 Pump House 424 413 97.41
3 Chlorination system 203 164 80.79
4 OHT 401 400/206 99.75
5 Distribution (Line Laying in Km.) 4559 4559 100.00
6 Solar Plant 401 357 89.03
7 F.H.T.C. 169013 155520 92.02
8 W.T.P.
9 ROAD DISMENTLING/RESTORATION(KM) 1655 1606 97.04
10 Villages where 100 % road restoration completed 97065 58955 60.74
11 Comissioning of Village 809 458 56.61
12 Regular water supply 809 453 56.00