Physical Progress
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Certified :
HO Villages :
Incoming Complaints Received
All Complaints :
Close Complaints :
Pending Complaints :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Detaile(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Agency Progress Details
Sr.No. District No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 Azamgarh 152 299 48835 40833 83.61% 40
Components Wise Physical Progress
Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 151 148 98.01
2 Pump House 151 148 98.01
3 Chlorination system 29 14 48.28
4 OHT 151 147/18 97.35
5 Distribution (Line Laying in Km.) 1591 1591 100.00
6 Solar Plant 126 71 56.35
7 F.H.T.C. 47692 40095 84.07
8 W.T.P.
9 ROAD DISMENTLING/RESTORATION(KM) 368 356 96.74
10 Villages where 100 % road restoration completed 97065 58955 60.74
11 Comissioning of Village 299 26 8.70
12 Regular water supply 299 55 18.39