Jal Jeevan Mission-Agency Dashboard

Heirarchy Details
Assign District:
Assign Scheme :
Assign Villages :
Physical Progress
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Certified :
HO Villages :
Incoming Complaints Received
All Complaints :
Close Complaints :
Pending Complaints :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Detaile(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Agency Progress Details
Sr.No. District No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 Chandauli 84 271 33558 28693 85.50% 145 3
Components Wise Physical Progress
Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 85 79 92.94
2 Pump House 85 70 82.35
3 Chlorination system 35 35 100.00
4 OHT 85 69/16 81.18
5 Distribution (Line Laying in Km.) 1048 920 87.79
6 Solar Plant 74 55 74.32
7 F.H.T.C. 33558 28693 85.50
8 W.T.P.
9 ROAD DISMENTLING/RESTORATION(KM) 894 887 99.22
10 Villages where 100 % road restoration completed 97065 58910 60.69
11 Comissioning of Village 271 100 36.90
12 Regular water supply 271 99 36.53